Aircon Commissioning Readings: The Record Nobody Asks For

Almost nobody asks an installer what the system read on the day it was commissioned, so almost nobody has those numbers. Their value shows up much later, when a fault has to be argued about and there is nothing to argue from.

By Team Snowflake | Updated 16 Sept 2026

What commissioning means, and what it is not

Commissioning is the point where a new system is proven to work correctly, not the point where it is switched on. Switching on shows that power reaches the unit and the fan turns. Commissioning shows that the sealed circuit was prepared properly, filled with the right weight of refrigerant, and running as the maker intended.

A brand new aircon blows cold on handover day almost regardless of how carefully it was put in. A shallow vacuum, a charge estimated instead of weighed, a service valve left part open: none of those stop cold air at the grille that first afternoon. What they do is shorten the life of the machine and raise running cost.

That gap is why commissioning has to be written down rather than felt. A walkthrough at sign-off is a good observation exercise, confirming each unit responds, drains and cools. It cannot confirm anything about the sealed circuit, because a sealed circuit shows no symptoms on the day it is filled.

Neither side is hiding anything here; the figures simply never come up. Owners do not know to ask, installers are not routinely asked, and a record nobody requests is a record nobody keeps. The result is a stock of Singapore flats whose original condition was never captured.

The readings that belong on the record

Five figures carry almost all of the later value. Each pins down a different part of the system at the one moment when everything was new, the installer was still in the flat, and the instruments were already out. Recorded together they describe a specific machine in a specific home.

The vacuum reached before charging is the only one that can never be recovered afterwards. After the gas goes in, the state the pipework was left in becomes unknowable. A written figure, with a note on whether it held after isolation, is the entire evidence trail for that step.

The weighed charge is the figure most often missing and most often needed. A split system ships with a factory charge sized for a nominal pipe length, and any run beyond that needs refrigerant added by weight. A proper record shows the factory figure, the addition for the actual run, and the total that went in.

Running pressures and the air temperature drop describe how the system behaved once it settled. Pressures from both sides go on the sheet with the outdoor conditions beside them, and that pair becomes the reference a future set of pressures is read against. The air temperature drop is the only line an owner can repeat alone.

Compressor running current closes the electrical side. A compressor draws a characteristic current for a given load, and that figure drifts as windings age, bearings wear, or the system is pushed harder than intended. Captured at commissioning, it becomes the line every later reading is measured against.

  • Reading recorded at commissioning
    Vacuum reached, and whether it stayed put
    What it pins down
    That the circuit was dry and sealed before charging
    What a later departure from it suggests
    Nothing later, which is exactly why it has to be captured on the day
  • Reading recorded at commissioning
    Weight of refrigerant charged in, including the pipe allowance
    What it pins down
    Exactly how much gas the system started with
    What a later departure from it suggests
    Gas has left the circuit, or was never fully put in
  • Reading recorded at commissioning
    Running pressures on both sides, with outdoor conditions
    What it pins down
    How the circuit behaved when everything was new
    What a later departure from it suggests
    A charge change, a restriction, or a compressor losing capacity
  • Reading recorded at commissioning
    Air temperature drop across each indoor unit
    What it pins down
    Delivered cooling per unit, repeatable by the owner
    What a later departure from it suggests
    Capacity is down somewhere, though not yet which part
  • Reading recorded at commissioning
    Compressor running current under settled load
    What it pins down
    The electrical signature of a healthy compressor
    What a later departure from it suggests
    Mechanical wear, a failing capacitor, or a system working too hard

Two more figures worth having if the technician took them

Superheat and subcooling belong on the same sheet whenever they were measured. They sit a level deeper than pressures, and between them they separate a genuine shortage of gas from a blockage that more gas will not clear.

Both figures move with operating conditions, so a bare number helps nobody. Whatever gets written down has to carry the conditions beside it: the mode, the fan speed, the set point, the room reading, and the weather outside.

A fault is a departure from a baseline

Every diagnosis is a comparison. A technician looks at what a system is doing and decides whether that counts as normal. Where a commissioning record exists, normal is a documented fact about this machine in this flat; where it does not, normal is an estimate from other machines.

That estimate is looser than most owners assume. Two units of the same model and capacity will not read the same once fitted. Pipe run length, how the outdoor unit sits, how much afternoon sun the ledge takes and what the room is doing all move the figures.

So a technician meeting a system new to them has to rebuild the baseline before any diagnosis. That rebuild is judgement, and judgement is where honest technicians differ. A commissioning record removes the rebuilding step, swapping an opinion about what normal should be for a measurement of what normal was.

This is the difference between a complaint and a case. A room that does not feel as cold as it used to cannot be tested, and it earns an opinion in reply. A temperature drop several degrees narrower than the commissioning figure, on the same fan setting, can be tested.

Why the warranty window turns on the record

The warranty period is where an absent record costs real money. A fault under cover raises one question ahead of every other: was the part defective, or was the system fitted and filled wrongly? Makers stand behind the first; installers stand behind the second. Nobody stands behind an argument that cannot be settled.

Without figures from the day, that question has no factual answer. A compressor that dies young might have failed on its own, or spent its whole life running against a wet circuit or a charge that was never right. Both stories fit the same dead compressor equally well.

With the figures, the question turns into arithmetic: three entries settle it between them. The vacuum was reached and it held. The weighed charge matches the nameplate plus the allowance for the pipe run. The settled pressures sit inside the window the maker states, which establishes that the system left commissioning in the state it was meant to be in.

Ask for the record in a form that survives. A photo of the gauge, a filled commissioning sheet, or a written summary in the installer's own message all work equally well. Verbal confirmation on handover day converts into nothing at the moment it is needed. Store it where the warranty card lives.

Ask at quotation, not at handover

Raise the readings while quotes are still being compared. An installer who knows the figures are expected turns up with the instruments and takes them as part of the job. An installer told at sign-off has nothing to write on, because the moment for capturing most of those figures has gone.

Asking early also changes the quotes in a useful way. Proper commissioning takes instruments, attention and a technician willing to stand behind what the gauge said. A quote priced with that in it reads differently from one priced without, and the difference is the information.

Put the request in writing at the point of acceptance, and keep it to what the installer should already be reading:

  • The final vacuum figure at the system, and how the gauge behaved once the pump was shut off
  • Nameplate charge, the extra weighed in for the pipe run, and the total in the circuit
  • Suction and discharge pressures once running had settled, with the outdoor conditions noted
  • Intake and outlet air temperatures at every indoor unit, with fan speed and set point beside them
  • Compressor running current, taken alongside the pressures rather than separately
  • Model and serial numbers of each indoor and outdoor unit, so the figures tie to the actual machines

What a straight answer looks like

The reply worth hearing describes instruments and a sheet, not reassurance. Firms that commission properly treat the request as ordinary, because they are being asked to write down work they already do. Firms that do not are being asked to start something new.

Push back on the answer that the system will be tested to make sure it is cooling well. Cooling well on the day is not a test of anything; it is the one outcome that happens whether or not the circuit was prepared and whether or not the charge was weighed. The room cannot tell you any of it.

If nothing was recorded on your system

Most systems in Singapore flats were handed over with nothing written down at all, and there is no way to go back for it. The vacuum figure is gone for good. The weighed charge is gone unless the installer kept a job sheet, which is worth one polite request.

The workable move is a baseline captured now, while the system is behaving. A baseline taken from a healthy machine does nearly the same job as one taken from a new machine, since the purpose is identical: to be the thing a future reading gets compared against.

Part of it needs no technician. The air temperature drop across each indoor unit, taken at a fixed fan speed with room conditions written beside it, needs one thermometer and no access to the sealed circuit. Repeat it now and then and the record builds itself. Everything on the refrigerant side needs gauges, which makes the next service visit the natural moment to ask.

Ask for those figures to be written down at a visit where nothing is wrong. A service report that captures a healthy system is among the most useful documents a homeowner can hold, and it is almost never requested. A visit where a fault is already present is the wrong occasion.

What a late baseline cannot settle

A baseline taken long after installation says nothing about how the system was fitted. It cannot show whether the circuit was properly emptied, whether the charge was weighed, or whether anything was wrong from the first day. Those questions close for good once the original figures go untaken.

What a late baseline does is protect everything from here forward. It turns the next fault into a comparison instead of a guess, gives a second opinion something concrete to work from, and puts a number on any slow decline. That is a smaller claim than a full commissioning record, and still worth the request.

Common questions

Which readings should an installer record at commissioning?
The vacuum reached and whether it held, the weighed charge including the pipe allowance, running pressures, the air temperature drop at each unit and the compressor current.
Why must the vacuum figure be taken on the day?
Once the gas goes in, the state the pipework was left in becomes unknowable, and no later test recovers that evidence.
Can a baseline be captured after the system is running?
Yes. A baseline taken from a healthy machine does nearly the same job for future comparison, though it cannot show how the system was originally fitted.
Which commissioning reading can an owner repeat alone?
The air temperature drop across an indoor unit, taken at a fixed fan speed with the conditions written beside it. It needs a thermometer and no access to the sealed circuit.
When should the installation record be requested?
At quotation, while quotes are still being compared. An installer told at handover has nothing to write on the sheet, because most figures cannot be captured later.

Sources

  1. Guidelines for Energy Efficiency of Air-Conditioning Systems (ACMV)

    National Environment Agency · Checked

    Testing and commissioning guidance for air-conditioning systems.