The exact renovation order for aircon works in Singapore
Most BTO and resale aircon headaches happen because trades arrive out of sequence. Mounting indoor units before carpentry or plastering traps fine dust in brand-new coils, while painting walls before Trip 1 leaves white PVC trunking clashing against freshly painted rooms.
Following the standard six-stage Singapore renovation order keeps every trade clear of the next and avoids double callout charges.
| Renovation stage | Trade on site | Aircon action required |
|---|---|---|
| 1. Site survey & layout | ID, homeowner, aircon contractor | Confirm unit spots, bed positions, wardrobe heights and ledge space |
| 2. Hacking & masonry | Hacking and wet-works crew | Complete wall hacking, screeding and toilet waterproofing first |
| 3. Aircon Trip 1 (first fix) | Aircon team + electrician | Run insulated copper, drain lines, trunking and 15A/20A isolator point |
| 4. False ceiling, L-box & carpentry | Ceiling crew and carpenters | Build around marked pipe paths; leave service clearances and access panels |
| 5. Wall & trunking painting | Painters | Paint walls and PVC trunking cleanly while fan coils are still boxed |
| 6. Aircon Trip 2 (second fix) | Aircon team | Mount indoor units and condenser, vacuum, charge and test every room |
Why first-fix piping must precede carpentry and ceilings
Carpenters need the exact drop height and horizontal path of aircon trunking before fabricating full-height wardrobes or kitchen top cabinets. Guessing clearances often results in wardrobe doors hitting indoor louvers or carpentry panels sealing off drain pipes permanently.
False-ceiling and L-box contractors also rely on Trip 1 to run concealed refrigerant and drain pipes inside the ceiling void while framing is open. Once plasterboard closes, rerouting a sagging drain pipe means cutting fresh ceilings open.
Painting before unit mounting avoids mismatched patches
Finishing at least the base and first finish coats of paint before Trip 2 lets painters coat the wall straight behind every fan coil backing plate and paint exposed PVC trunking smoothly without masking delicate plastic aircon louvers.
If painters wait until after indoor units hang, paint specks land on coils and unpainted rectangles show up years later whenever you replace the system with a differently sized indoor unit.
Final checks before signing off unit commissioning
Keep the renovation site broom-clean before Trip 2 so the fresh units are not tested in thick dust. Confirm with your interior designer that no heavy sanding or chemical floor acid-washing remains after aircon commissioning.
Snowflake Aircon Services coordinates Trip 1 site mark-ups directly with homeowners and interior designers across HDB and condo renovations, catching clearance clashes on paper before a single hole is drilled.
Common questions
Should aircon be installed before or after painting in an HDB renovation?
Does aircon piping go in before or after built-in carpentry?
Can we run aircon Trip 1 before wall hacking finishes?
How early should I book my aircon contractor for a BTO renovation?