On this page
Quick summary
A flat with a 40A main switch, or one upgraded under MUP or HIP, needs no aircon permit. A 30A flat needs one only when the job adds a new 15A point or 20A isolator. HDB's installer, reporting and placement rules apply either way.
1. Check Your Block's Electrical Loading First
HDB gives blocks completed on or after 1 January 1994 a 40A main switch. Blocks upgraded under the Main Upgrading Programme or Home Improvement Programme are in the same group. HDB says owners of these flats need not apply for a permit to install an aircon or other higher-capacity equipment.
The permit question is a loading and wiring question, not a universal requirement. If the loading is unclear, use HDB's electrical-load checker. Under HIP, permit status sits beside access and reinstatement in the aircon plan before HIP renovation starts.
2. In 30A Flats, the Permit Depends on the Electrical Point
HDB sets no permit requirement in two cases. One is when the installation uses an existing approved 15A power point. The other is when it uses an existing 20A isolator provided by the owner or HDB.
An electrical permit is required before installation when the job needs a new 15A power point or a new 20A isolator. The same aircon job is permit-free or permit-triggering depending on whether an approved point already exists.
| 30A flat scenario | Permit status | What HDB says |
|---|---|---|
| Use existing approved 15A point or 20A isolator | No permit | Installation can proceed without an electrical permit |
| Need new 15A point or new 20A isolator | Permit required | Apply for electrical permit before installation starts |
| Not sure what the block has | Check first | Use HDB's electrical-load checker before approving the job |
3. Rules Still Apply Even Without a Permit
These HDB conditions apply whether or not a permit is needed:
- A BCA-trained aircon installer must do the installation.
- New wiring goes through SP Services Form CS/5H, endorsed by HDB for testing.
- An installation report goes to the HDB Branch managing the flat within 14 days after installation.
- The ledge is for the condensing unit only, all piping runs internally, and no unit sits along the common corridor.
- Condensation water drains into a nearby floor trap inside the flat.
- Running current must stay within the approved electrical rating, and the condensing unit base needs rubber padding.
- No openings are hacked through reinforced concrete, and no pipes are embedded in slabs, columns or beams.
4. 40A and Upgraded Flats Have Their Own Limits
A 40A or upgraded flat still has limits. Running current is restricted by a 20A double-pole isolator or a 15A power point. HDB allows a maximum of two split-type condensing units, one wall-mounted unit per wall panel, and 110 kg per wall panel on the external wall or the ledge.
A quote can be permit-free and still break these layout or load limits. The permit is one part of the install review.
HDB Rules vs Safety Items vs Contractor Advice
A contractor's "required" covers three different things. An HDB rule is a condition HDB sets on work in your flat. A safety item is a code or licensing practice, such as refrigerant handled by a licensed technician. Contractor advice is a preferred method, not a rule.
Service intervals are not set by HDB. They follow usage, air quality and unit condition. Whether old piping can be reused follows its age, wrapping condition and what the new unit's specification calls for.
Two quotes may differ in price. Check whether both include the same mandatory items before reading the cheaper one as better.
5. Verify Compliance Items Before Approving the Quote
Settle three points before approving a quote. First, the block's loading. Second, whether the job uses an existing approved point or a new one. Third, who handles the wiring test, the installation report, placement, drainage and current limits.