Ceiling cassette or ducted aircon for an office?
Snowflake Aircon Services recommends cassettes when the floor is open and the panels can show, and ducted units when the space is split into rooms or the fit-out needs a clean ceiling with only grilles. The table sets out why.
| Ceiling cassette | Concealed ducted | |
|---|---|---|
| Best fit | Open-plan office, shop floor, showroom | Partitioned offices, clinics, a retail fit-out with a clean ceiling |
| What shows | A panel in the ceiling | Grilles or slot vents only |
| Airflow | Out of the panel, adjustable per outlet on some models | Through ducts to each room's grille |
| Filter access | Behind the panel, from the room below | At the unit or the return grille, through a ceiling access opening |
| A fault at the unit | Affects the area under that cassette | Affects every room the unit feeds |
Ceiling depth
Both need a ceiling void, and the published body heights are close. Daikin's SkyAir tables list round-flow cassette bodies of 256 mm and 298 mm with a 50 mm decoration panel, and its middle static pressure ducted range at 245 mm. Mitsubishi Electric describes a 250 mm thin body for its Mr Slim ceiling cassette.
The body height is not the whole depth. The duct, the drain fall and the supports take space too, so a ducted layout needs its void checked along the duct route, not only above the unit.
How the space is used
Open floors favour cassettes. Daikin lets each outlet on its round-flow cassette be set from position 0 to 4, so air can be steered away from a desk or a doorway.
Partitioned rooms favour ducted units. One concealed unit can feed several small rooms through separate grilles, where a cassette in each room means more units to buy and service.
Servicing and downtime
A cassette is serviced from a ladder in the room it cools, with the panel lowered. A ducted unit is serviced through an access opening, and the room below is covered while the work runs. Plan servicing around trading hours, and settle the access position before the ceiling is built.
SS 553:2026 is Singapore's code of practice for air-conditioning and mechanical ventilation in commercial, office and institutional buildings. Check the building's fit-out rules for where units and grilles may go.