New BTO, One Warm Bedroom: Wardrobe Blocked Intake Air
One bedroom in a new flat runs warm and rework is proposed. Whether the install was wrong or the room changed after it.
By Team Snowflake | Updated 24 Aug 2026
Teaching case based on recurring Snowflake service patterns; identifying details are combined.
What gets specified
A new flat with indoor units positioned and joinery being designed around them. One bedroom is to receive a full-height fitted wardrobe running right up to the ceiling. The aircon layout and the joinery drawing exist entirely separately.
- Setup
- Midea Multi-splitNew installHDBTengah
- Misread as
- A newly installed unit that underperforms from the start, with rework needed in a finished room.
- Check first
- The joinery drawing laid over the services drawing before either is signed off
What the drawing does not show
An indoor unit draws air in along its top and front, and it needs clear space there to do it. That requirement is published as a minimum clearance and it is almost never carried onto a joinery drawing. Comparing the two before anything is built takes a few minutes, and it is the only point at which the problem is cheap to solve. Once the wardrobe is fitted, every remaining option costs real money.
Minimum clearances published for the indoor unit define the space its intake actually requires.
A full-height wardrobe finishing close beneath the unit reduces that space below the stated figure.
Separate aircon and joinery drawings mean neither party sees the conflict on their own sheet.
A room that would run warm from the very first day, without any fault existing, follows from the two combined.
Why it goes wrong
Services are set out early and interiors are designed later, and the two drawings are rarely laid over each other. A joiner working to a wall elevation sees a ceiling to build up to, not an intake to keep clear. Nothing about either decision is unreasonable on its own. The failure is that nobody compares them, and the consequence is discovered only when the room does not cool.
What the fix involves
The wardrobe is stopped short of the clearance the unit requires, or the unit is repositioned before joinery is made. Either costs almost nothing at drawing stage. The habit worth adopting is to lay the joinery drawing over the services drawing before either is signed off, because that overlay is where every clash of this kind becomes visible.
How to tell it worked
Clearance measured on site once the joinery is installed, against the published figure rather than by eye. A gap that looks generous from the floor is often well under what the unit needs.
Before you sign off
Lay the joinery drawing over the services drawing
- Indoor units need published clearance at the intake. Joinery drawings do not carry that figure.
- Both decisions are reasonable alone. The failure is that nobody compares the two sheets.
- At drawing stage the fix is free. After the wardrobe is fitted, every option costs money.
Related diagnostics
Questions this case answers
One bedroom in my new BTO is warmer than the others, is the aircon faulty?
Can carpentry affect how well an aircon cools?
How much space does an aircon indoor unit need around it?
What should I keep from my BTO aircon handover?