Quick summary
Resale HDB aircon installation works cleanly in two stages: remove old units before hacking, run first-fix copper and drains right after masonry, and mount indoor heads after painting. Sequencing pressure tests before false ceilings and carpentry prevents hacked box-ups and hidden leaks.
Why Resale HDB Aircon Work Splits into Two Trips
Most resale HDB renovations strip out 10-to-20-year-old copper lines, hack bathroom tiles, and build new ceiling pelmets or wardrobes. Leaving old indoor fan coils on dusty walls during hacking fills coils with fine cement grit.
Splitting the job into a first-fix piping trip and a second-fix mounting trip protects new equipment. Technicians lay fresh SWG 22 copper, Class 0 insulation, and 16mm drain pipes cleanly before carpenters box anything up.
Indoor heads and the outdoor condenser go up only after wet works and primer coats finish, keeping fans spotless on handover day.
Follow the Resale HDB Hacking and Piping Sequence
Align your HDB-registered renovation contractor and aircon installer around these five milestones so trades never block each other:
Scroll to see more columns
| Renovation stage | Aircon task to complete | Trade dependency | Key quality or HDB check |
|---|---|---|---|
| Pre-hacking survey | Confirm pipe route, drain trap, amps | Before HDB permit hacking starts | Check HDB renovation permit and beams |
| Dismantle and hacking | Strip old units and rusted brackets | Ahead of wall and floor hacking | Seal electrical isolator safely |
| First-fix piping (Trip 1) | Lay copper, Class 0 foam, PVC drains | After masonry, before ceiling box-up | Run nitrogen pressure and water flow test |
| Carpentry and painting | Keep pipe stubs capped and masked | During pelmet and wardrobe build | Leave clearance around indoor mounts |
| Second-fix mounting (Trip 2) | Mount FCU, ODU, vacuum, commission | After final dust-free paint coat | Lodge HDB Form AC-02 within 14 days |
Prevent Concealed Leaks and Beam Breaches During First-Fix
HDB strictly bans hacking or core-drilling structural columns, beams, and household shelter walls. Plan trunking turns around beams during your site survey so installers never pause mid-job.
Never reuse old R22 or R410A copper pipes for a modern R32 inverter unless a full pressure test and wall-thickness check proves they are sound. Old thin-wall pipes trap stale oil and risk pinhole leaks behind brand-new cabinetry.
Confirm that your carpenter leaves at least 100mm of top clearance above every wall-mounted fan coil so air intake and future chemical washes stay unobstructed.
Plan Your Survey Booking and First-Year Servicing Costs
Locking in your survey before demolition avoids last-minute rerouting charges and sets up clean post-renovation upkeep:
- Reserve a S$30 pre-hacking site check so installers mark beam detours and trap falls early; that fee vanishes once you book installation.
- Post-move-in routine washes stay affordable: S$50 on 1 head, S$30 per head on 2, and S$25 per head on 3-plus bookings, each carrying a 14-day warranty.
- Clearing stubborn plaster dust via chemical wash bills S$80 (1 head), S$70 apiece (2 heads), or S$60 apiece (3-plus heads) under 60-day warranty terms.
- When deep tear-downs are needed years later, overhauls run S$150 (1), S$125 each (2), or S$115 each (3-plus) with 90-day cover; S$30 fault checks drop to zero if repair goes ahead.