Aircon Cable Size: The Decision Buried Behind the Wall
Nothing about a cable announces its size once the plaster is on. It was either worked out against the load, the route and the conditions it runs through, or it was carried over from the last job that looked similar.
By Team Snowflake | Updated 16 Sept 2026
What the conductor is actually chosen against
Cable size follows the circuit, not the machine. The figure that ends up on a drawing is the output of several separate questions, and the aircon answers only one of them. How much current the load draws is the starting point. How the cable is installed, what else runs beside it, how warm that space gets, and how far the run travels all move the answer afterwards.
Singapore settles this in one document. SS 638 is the standard governing electrical installations, and its cover carries the line [Formerly CP 5] because SS 638:2018 re-designated the third revision of CP 5. The current edition is SS 638:2018+C1:2020+A1:2022, so a specification still citing CP 5 is citing a designation retired in 2018.
That code splits the cable question the way a designer splits it. The inputs sit in its opening principles: nature of demand, environmental conditions, type of wiring and method of installation, and cross-sectional area of conductors. Wiring systems and overcurrent protection get chapters of their own, because the cable and the switch guarding it are settled against the same circuit.
A code can be voluntary and still bind. The standard carries a note saying a Singapore Standard is voluntary unless a regulatory authority makes it mandatory, and EMA is that authority here. It names SS 638 as the standard adopted for electrical installations under the Electricity (Electrical Installations) Regulations. The code is not a trade preference but the yardstick the work is measured against.
The honest reply to what size cable an aircon needs is that the question is incomplete. Two identical machines in two flats can properly land on different conductors, because the route and the conditions differ. Anyone who answers from a model number alone has skipped every input except the first.
| What goes into the decision | What it changes | Who holds the answer |
|---|---|---|
| The current the system actually draws | Sets the floor the conductor has to carry continuously | The equipment data for that model |
| The protective device it sits under | The two are chosen as a pair, so neither moves alone | The circuit designer, not the aircon installer |
| How and where the cable is installed | Decides how easily heat leaves the copper | Whoever has actually seen the route |
| What else shares the trunking or the void | Grouped circuits warm each other and derate the run | Whoever knows what is already in there |
| The length of the run | Governs how much voltage is lost on the way | Measured on site, never read off a plan |
- What goes into the decision
- The current the system actually draws
- What it changes
- Sets the floor the conductor has to carry continuously
- Who holds the answer
- The equipment data for that model
- What goes into the decision
- The protective device it sits under
- What it changes
- The two are chosen as a pair, so neither moves alone
- Who holds the answer
- The circuit designer, not the aircon installer
- What goes into the decision
- How and where the cable is installed
- What it changes
- Decides how easily heat leaves the copper
- Who holds the answer
- Whoever has actually seen the route
- What goes into the decision
- What else shares the trunking or the void
- What it changes
- Grouped circuits warm each other and derate the run
- Who holds the answer
- Whoever knows what is already in there
- What goes into the decision
- The length of the run
- What it changes
- Governs how much voltage is lost on the way
- Who holds the answer
- Measured on site, never read off a plan
Why the same size behaves differently in two flats
Copper warms as it carries current, and whether that warmth can escape is the design question. A cable clipped to a surface in moving air sheds it easily; the same cable buried in a chase, sleeved in conduit, or lying against thermal insulation sheds it slowly. Nothing about the conductor has changed; what changes is how much it can carry before its insulation ages.
Bundling makes that worse. Several circuits run together in one trunking each warm the space the others occupy, so the group carries less than any single member would alone. A renovation that consolidates cable routes for neatness can quietly reduce what every run in the bundle is good for.
Ambient heat is the input Singapore supplies for free. A ceiling void under a flat roof, a service riser, a run along an unshaded ledge: each sits warmer than the room. Warmer surroundings leave the copper less margin before it reaches the same limit, so a cable specified against a temperate assumption was specified against the wrong climate.
Equipment manuals know none of this, and they say so. The Daikin installation manual covering the R32 split series and models FTXM35K3V1B, FTXM42K3V1B and FTXM50K3V1B, requires electrical work to follow relevant local and national regulations and its own instructions. It also requires a dedicated power supply circuit and the specified wires. What no manual can supply is the route, the grouping and the ambient conditions in one particular flat.
The conditions a cable was sized against can move
A conductor gets chosen against the flat as it stood on the day. The flat does not hold still. Later work adds circuits to the same trunking, boxes a run into a bulkhead, or drops a false ceiling over a route that used to breathe.
None of that touches the cable, and all of it changes what the cable is good for. The original decision can have been correct and the situation around it have shifted since, a different failure from a bad first decision that produces the same warm copper.
It also explains a pattern that looks like coincidence. A circuit behaves for years, then reports trouble after a renovation that never went near the aircon. The trades who changed the conditions had no reason to think about that run, and nobody was asked to check it afterwards.
Volt drop: the second test a cable has to pass
A cable can be thick enough to avoid overheating and still too thin to do its job. Copper has resistance, and current pushed through resistance loses voltage on the way, so the machine at the far end sees less than the board does. That loss grows with the length of the run and the current drawn.
Thermal capacity and delivered voltage are separate tests, and a run can pass the first while failing the second. The code treats them that way. SS 638's cable appendix is titled current-carrying capacity and voltage drop for cables, holding both properties of one conductor in a single place because both have to be satisfied. Sizing up a long run is therefore not generosity. It is the second test doing its work.
A compressor feels this more than any other household load. It draws hardest in the instant it starts, when a sagging supply has the least to give. Whether a soft starter belongs on that machine is settled elsewhere. What belongs here is simpler: a long, marginal run can make a healthy system behave badly, and the system gets blamed.
The limit itself is a number, and it belongs in the code and not on this page. SS 638 is a paid standard. Its front matter and contents are public, which is where the appendix title above comes from. The provisions are not public, and any figure quoted without that document open has come from memory or from somebody else's blog.
Where the length of the run actually comes from
Length is the input owners never think to mention. The run is decided by where the board sits and where the outdoor unit ends up, and both get settled for reasons unconnected to electricity.
Moving the condenser to the far end of a ledge for noise, clearance, or to keep it off a neighbour's window lengthens the circuit as a side effect. Nobody announces that as an electrical decision, but it is one, taken when changing it still costs nothing.
Why undersizing does not announce itself
An undersized conductor performs on installation day. It carries the current, the room cools, and the handover shows that the system runs. What the handover cannot show is anything about the cable, because nothing on that day asks the cable a hard question.
The evidence that would settle it sits out of the household's reach. The conductor sits behind plaster, inside trunking, or above a ceiling nobody opens. Its temperature is invisible. No appliance reports it, no bill separates it, and no symptom in the room names it. A homeowner has no instrument here, which is a fact of the installation, not a failing.
What surfaces later is a pattern instead of an event. Trips that cluster in the hottest stretch of the year and stay away through the rest of it. Behaviour that follows the weather more closely than it follows the machine. Those reports get read as an ageing aircon, because the aircon is the visible thing, so the money goes there first.
Nothing observed from inside the room separates the two candidates. A machine near the end of its life and one on a marginal supply read alike from a sofa. Settling it means measuring at the board and at the equipment with the load running, so hand over a note of when the trouble appears rather than a theory about which part failed.
One shortcut turns a hidden weakness into a live one. The conductor and its protective device were chosen as a pair, so the aircon breaker rating describes the cable behind it. Fitting a larger device after repeated trips leaves the conductor where it was and raises the level at which anything intervenes.
| Moment | What it proves | What it leaves untested |
|---|---|---|
| Handover on installation day | The system runs and the room cools | Everything about the cable feeding it |
| The first hot stretch of the year | The circuit is being asked for more than usual | Whether the margin was thin from the start |
| A trip that keeps coming back | Something on that circuit has passed a limit | Which side of the limit, the load or the conductor |
| Replacing the system years later | The old machine had reached its end | Whether the new one suits the run it inherits |
- Moment
- Handover on installation day
- What it proves
- The system runs and the room cools
- What it leaves untested
- Everything about the cable feeding it
- Moment
- The first hot stretch of the year
- What it proves
- The circuit is being asked for more than usual
- What it leaves untested
- Whether the margin was thin from the start
- Moment
- A trip that keeps coming back
- What it proves
- Something on that circuit has passed a limit
- What it leaves untested
- Which side of the limit, the load or the conductor
- Moment
- Replacing the system years later
- What it proves
- The old machine had reached its end
- What it leaves untested
- Whether the new one suits the run it inherits
The circuit outlives the machine
Aircon systems get replaced and circuits do not. A replacement lands on a conductor chosen for the machine that came out, under conditions that may have moved since. More indoor units on one condenser, a larger outdoor unit, or another circuit added to the same trunking in a later renovation all change the arithmetic without anyone touching the cable.
Replacement day is the natural moment to re-ask the question. It is also the one that gets skipped. The old system worked, so the supply is assumed to have been adequate, and the new one goes onto the same run. That assumption is reasonable and it remains an assumption. It carries forward whatever was decided the first time, including a decision that was never really made.
What an owner can establish is narrower than a size and more useful than one. Not what the conductor ought to be, but whether anybody worked it out. A circuit that was designed leaves evidence behind it, because someone specified it, tested it and put a name to it. A circuit that was assumed leaves a working aircon and nothing else.
Singapore makes that evidence easy to ask for. EMA tells consumers that electrical work at home or in the office should be carried out or supervised by a licensed electrical worker, and installation, repair or modification of wiring falls inside that. The work must then be tested and certified safe for use by a licence holder of the appropriate class. Check the worker's card before any of it starts, as EMA advises.
This page will not produce a size, and that is deliberate. Sizing a circuit is design work, done against the code with the route and the conditions in front of the person doing it. A contractor who names a cable size from a photograph and a model number is guessing at four of the five inputs. The question worth putting to a quotation is not what size, but who worked it out and against what.
What a replacement quote can settle, and what it cannot
A quote for a new system prices equipment and labour. It does not, on its own, revisit the supply, and most quotes make no claim to. Asking whether the existing circuit is being inherited or reassessed is a fair question and a short one.
The answer separates two kinds of contractor. One treats the supply as somebody else's finished work; the other treats it as an input to confirm before a machine is ordered. Both may install well, but only the second has looked at what stays in the wall after everyone has left.
Common questions
What size cable does an aircon need?
Why does the same cable carry different currents in two flats?
Can a cable be thick enough and still fail the circuit?
Why does an undersized cable show no symptoms at handover?
Sources
- Renovation Guidelines for Electrical Works
Housing and Development Board · Checked
HDB electrical works conditions, including power point permits and licensed workers.
Ready to get started?
Tell us what’s going on. Symptoms, setup, photos, anything we should know. We’ll assess and come back with the right next step.