Aircon Checks Before an HDB Renovation, Step by Step

A renovation is the cheapest moment to fix an aircon's piping, power and positions, because the walls are open. The decisions made before it starts set what goes right after it.

On this page

The aircon checklist for an HDB renovation

Decide the aircon plan before the contractor starts hacking, protect the units during the work, and service them before moving back in. The list below follows that order.

Aircon jobs around an HDB renovation
JobOur rate
Site survey before the renovation$30 / visit
Pressure test on piping you plan to keepQuoted per job
Chemical servicing after the renovation, per wall-mounted unit$80 for one unit; $70 each for two; $60 each for three or more

The site survey fee is waived if you go ahead with the installation quoted after it.

Our rates are from our rate card.

Before the renovation

1. Decide whether each unit stays, moves or is replaced. 2. Fix the indoor unit positions and the piping route with the carpenter. 3. Pressure test any concealed piping you plan to keep. 4. Check the power points or isolators suit any new outdoor unit. 5. Confirm the drain ends at a floor trap in the flat.

During the renovation

6. Remove units that are being replaced before hacking starts. 7. Cover the units that stay, and keep them switched off during dusty work. 8. Keep the aircon ledge clear; HDB does not allow it to be enclosed or used for anything but the outdoor unit.

After the renovation

9. Install new units after the carpenter has framed the false ceilings, before final painting. 10. Book a chemical service for units that stayed, after the dust is cleaned up. 11. Submit HDB's installation report within 14 days of any new installation.

Why the piping route matters most

HDB does not allow aircon pipes to be embedded in reinforced concrete slabs, columns or beams, and all piping must run inside the flat. A route agreed with the carpenter can be hidden in boxing or a false ceiling instead.

Agree it before the carpentry is built. Changing the route afterwards means opening the finished work.

Power and the ledge

A larger new system may need a different power point or isolator, which a licensed electrical worker fits and tests. Flats in older blocks without the higher electrical loading need a permit from HDB before new aircon points are added.

Check the ledge can take the new outdoor unit before buying. HDB limits flats with the 40A loading to two split-type condensing units.

Common questions

Does a 30A HDB flat need a permit for new aircon points?
Yes, for new points. An HDB flat without the higher electrical loading needs an HDB electrical permit before a new 15A power point or 20A isolator is installed for the aircon. Using an existing approved point needs no permit, so check the main switch before the renovation.
Can aircon piping be hidden during an HDB renovation?
Yes, in boxing, a false ceiling or trunking, but not in the structure. HDB does not allow aircon pipes to be embedded in reinforced concrete slabs, columns or beams, and all piping must run inside the flat. Agree the route with the carpenter before the boxing or ceiling is built.
When should the aircon installer come during an HDB renovation?
The aircon installer should come after the carpentry and false ceilings are framed, so the piping route is built into them, and before the final painting. Old units being replaced should be removed before hacking starts. Agree both dates with the renovation contractor at the start.
What aircon paperwork does HDB need after a renovation?
HDB needs an installation report submitted to the HDB branch managing the flat within 14 days after any new aircon installation, and the installer needs BCA training. New wiring also needs an SP Services form endorsed by HDB for testing, which the licensed electrical worker arranges.